CE-1008
A. After tower has been fully erected, remove erection davit and lower it to the
ground.
B. Use tab line to lift the following parts and install on the tower in the order
listed:
1. Horizontal cable brace (2)
2. Spacer (4)
3. Anti-twist guy assy (8)
4. Box - lifting davit (4)
5. Outboard support (4)
6. Grip-strut platform (4)
C. Remove horizontal cable braces after guys have been installed and properly
tensioned.
Figure 2-6. 80-Foot Tower Erection, Sheet 15 of 18
2-35