CE- 1008
A.
Leave lifting harness installed on section.
B.
Pull up enough slack in hoist line and tie off to a vertical member clear
of davit.
C.
Tip davit to a vertical position and lift hooks clear.
D.
Use hand-over-hand method and raise davit to next position.
E.
Install remaining tiedown cables to base section.
Figure 2-6. 80-Foot Tower Erection, Sheet 11 of 18