TM 11-5985-362-13
Once alined, leave wire on the ground and return to reeling machine. Attending crewmember at reeling machine
holds SLEEVE with marker tag 7.
Two crewmembers remove axle with REEL NO. 4 and walk toward clamp 3 on the CENTER LAYOUT WIRE until
SLEEVE with marker tag 3 is free of reel.
Insert SLEEVE with marker tag 3 into CLAMP 3. Tighten clamp wingnut securely.
Crewmember from reeling machine moves to CLAMP 3 on CENTER LAYOUT WIRE and holds it in position.
Two crewmembers with axle walk to SLEEVE with marker tag 7 at left end of BACK LAYOUT WIRE until SIDE
LAYOUT WIRE is free of reel.
Return empty REEL NO. 4 to antenna transit case and obtain two 30 inch anchors.
Position one crewmember at CLAMP 3, and one at the TOWER BASE to hold wires in position.
Apply tension to left side ends of the SIDE and BACK LAYOUT WIRES to form a triangle.
With one 30 inch anchor mark point where the ends (SIDE and BACK LAYOUT WIRES) with marker tag 7 meet.
Leave anchor for later installation (LEFT SIDE ANCHOR 7).
Proceed to right side ends (SLEEVE with marker tag 7) of SIDE and BACK LAYOUT WIRES and mark point with
other 30 inch anchor for later installation (RIGHT SIDE ANCHOR 7).
2-18