TM 11-5985-362-13
SECTION IV. REMARKS
REFERENCE
REMARKS
CODE
A
TOTAL ANTENN A INSTALLATION WITH 6-MAN CREW INCLUDING SITE
LAYOUT, ANCHOR EMPLACEMENT, ANTENNA ASSEMBLY AND ERECTION.
B
OPERATOR WALKAROUND VISUAL INSPECTION OF TOTAL ANTENNA
FOR STRUCTURAL AND PHYSICAL INTEGRITY.
C
OPERATOR VERIFICATION THAT REFLECTED POWER AT TRANSMITTER
IS WITHIN LIMITS.
D
OPERATOR/CREW RETENSIONING OF TOWER GUYS AS REQUIRED.
E
SIX-MAN CREW REPLACEMENT OF ANTENNA AT SAME SITE USING
F
OPERATOR VISUAL INSPECTION OF ANTENNA COUPLER SPARK GAP
AFTER ELECTRICAL STORM F OR SIGNS OF PITTING OR CARBON TRACE.
G
OPERATOR CLEANING OF ANTENNA COUPLER SPARK GAP IN THE
EVENT OF EVIDENCE OF PITTING OR CARBON TRACE RESULTING FROM
ARCING DURING ELECTRICAL STORM. TIME INDICATED INCLUDES
RE-GAPPING AS NECESSARY.
H
OPERATOR/CREW REPLACEMENT OF ANTENNA COUPLER WITH
EQUIVALENT UNIT.
I
USE OF RF VECTOR IMPEDANCE METER (HEWLETT-PACKARD 4815A
OR EQUIVALENT) TO MEASURE ANTENNA COUPLER VSWR TO DETER-
MINE IF IT IS GOOD OR BAD. ANTENNA COUPLER IS NOT REPAIRABLE.
J
OPERATOR/CREW REPAIR OF WIRES OF ANTENNA CURTAIN USING
WIRE REPAIR PARTS KIT (245-WIR-01T) OR WIRE SPLICE KIT
(246-WIR-01T) CONTAINED IN START-UP SPARES. TIME INDICATED
INCLUDES LOWERING AND RAISING OF ANTENNA BY A CREW OF 6
FOR ACCESS.
K
OPERATOR/CREW REPAIR RESTRICTED TO REPLACEMENT OF DEFEC-
TIVE ANTENNA SUPPORT COMPONENTS CONTAINED IN START-UP
SPARES, I.E., MAST SPLICES (006-SPL-01A) AND MAST BASE PINS
(016-BLT -16P).
L
REPLACEMENT OF MAST INSULATOR (087-INS-01A) ON MAST TOP
PLATE FROM TWO- YEAR SPARES KIT.
M
OPERATOR TEST OF MAST LIGHT ASSEMBLY OPERATION BY COVERING
AND UNCOVERING REMOTE PHOTOCELL AND VISUALLY VERIFYING
OPERATION OF RELAY IN CONTROL BOX AND/OR ON AND OFF CYCLING
OF DOUBLE OBSTRUCTION LIGHT ASSEMBLY .