Two crewmembers proceed to antenna transit case and each obtain a MAIN FEEDLINE WINCH and cable
clamp WRENCH.
One crewmember proceeds to original ANCHOR 1, the other to original ANCHOR 6.
Attach MAIN FEEDLINE WINCHES to original ANCHORS 1 and 6 .
Attach wire/cable grippers of MAIN FEEDLINE WINCHES at ANCHORS 1 and 6 to MAIN FEEDLINE.
Apply enough tension (by cranking winches) to MAIN FEEDLINE to allow removal of cable clamps.
Using wrenches, remove CABLE CLAMPS on MAIN FEEDLINE at ANCHORS 1 and 6.
(Refer to page 2-6 for procedure.) Disconnect the VERTICAL FEEDLINE and VERTICAL CATENARY from
their pound-in anchors.
Remove tension completely from the MAIN FEEDLINE with MAIN FEEDLINE WINCHES.
Disconnect MAIN FEEDLINE WINCHES at original ANCHORS 1 and 6.
Relocate and attach to new
ANCHORS 1 and 6.
With one crewmember at each original ANCHOR 7 (RIGHT and LEFT SIDE), disengage the rope tensioners
of BACK RADIATOR GUYS AND CATENARIES from their anchors. (Refer to page 2-5 for operation.)
Keep a slight tension on the RADIATOR GUYS and CATENARIES.